    18 CS615 assignment no 4 fall 3 January 2012 virtual university solution soon

    Cheap Webhosting
    Decent Software House is wanted to develop software for a client on demand. The WBS of the software activities is given as in figure 01.
    There are given some tasks of a software development life cycle. Software project life cycle start the task (1) and end at task (7).

    Keep in mind the above scenario and answer the below given questions:
    Q.01 If Task (3) starts two days late, what is the effect on the project end date? Why?
    Q.02 What is the critical path for this project, and what is the duration of the critical path? Why?
    Q.03 How many days can Task (4) be late in starting without affecting the project completion date? Why?





  2. #2
    Junior Member
    Join Date
    Jan 2011
    Posts
    2
    Thanks
    0
    Thanked 0 Times in 0 Posts
    CS615 assignment 4 ka solution jaldi upload karden dears

  3. #3
    Administrator
    Join Date
    Oct 2011
    Posts
    494
    Thanks
    1
    Thanked 30 Times in 21 Posts
    kisi nay ki ho gi tu upload karay ga i guess.
    03009520262
    Rabeel Website

  4. #4
    Super Moderator Vuhelper's Avatar Users Flag!
    Join Date
    Apr 2011
    Posts
    17,537
    Thanks
    15
    Thanked 96 Times in 87 Posts
    The Critical Path Method (CPM)
    Quality Tools > Tools of the Trade > 16: The Critical Path Method (CPM)

    In the Activity Diagram described in the previous article, a network of tasks were set up to show the dependent sequence of activities within a project. The Critical Path Method can be applied to such as network to answer the most common question asked of project managers: How long will the overall project take?

    Some 'project management' computer programs, such as Microsoft Project, will calculate the critical path for you. You can also do it by hand or build a spreadsheet to calculate it, using the method described below.

    How does it work?
    In the Activity Diagram described in the previous article, a network of tasks were set up to show which tasks needed completion before other tasks could be started. A very common next step is to add timings to show how long each task will take and then to identify the critical path, which is the route through the network that will take the longest amount of time.

    Tasks which are not on the critical path have more leeway, and may be slipped without affecting the end date of the project. This is called slack or float.

    Tasks on the critical path have no slack and this feature may be used to actually identify the critical path. It is also quite common to have more than one critical path: indeed, the perfectly balanced project is all critical path.




    A critical path


    It may be possible to reduce the critical path of a project (and consequently pull in the completion date) by rearranging some tasks which have an optional sequence or by moving key people onto tasks in the critical path so you can reduce the time for these tasks.

    How do you do it?

    1. Build an Activity Diagram, as described in the previous article, including estimating the time required (or duration) for all tasks. Include a space on each task card for early and late start and finish dates or times (times, rather than dates, are required for tasks where hours or minutes are significant).

    The early start and early finish are simply the earliest times that a task can start or finish. The late start and late finish are the latest times that a task can start or finish.

    2. Starting with the tasks at the beginning of the diagram, complete the early start and early finish for each task in turn, following the arrows to the next task, as in the figure below. The early start of a task is the same as the early finish of the preceding task. If there is more than one predecessor task, then there are several possible early start figures. Select the largest of these. The early finish for each task is equal to the early start plus the duration of the task. The final calculation is for the earliest completion time for the project. This is calculated in the same way as the early start date.




    Calculating the early start and finish


    3. Starting with the tasks at the end of the diagram, calculate the late start and late finish for each task in turn, following the arrows in the reverse direction to the previous task, as in the diagram below. The late finish is the same as the late start of the succeeding task (for the final tasks in the project, this is equal to the earliest completion date). If there is more than one successor task, then there are several possible late figures. Select the smallest of these. The late start for each task is the late finish minus the duration of the task. The final calculation is for the earliest completion time for the project. This is calculated in the same way as the early start date.



    Calculating the late start and finish


    4. You now have, for each task, the earliest and latest times that it can start and finish. Now find the slack time (or 'float') for each task by subtracting the early start from the late start. The slack time is the amount of time the task can be slipped by without affecting the end date of the process. The critical path can now be identified as all paths through the network where the slack time is zero.




  5. #5
    Administrator
    Join Date
    Oct 2011
    Posts
    494
    Thanks
    1
    Thanked 30 Times in 21 Posts
    lo g app ka solution ah gia hai ab mooj karo.
    03009520262
    Rabeel Website

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

     

Similar Threads

  1. Replies: 2
    Last Post: 01-04-2012, 07:16 AM
  2. Replies: 0
    Last Post: 12-31-2011, 01:04 AM
  3. Special virtual university assignment solution
    By Xpert in forum Assignments & Solutions
    Replies: 15
    Last Post: 12-27-2011, 09:42 PM
  4. Replies: 1
    Last Post: 10-31-2011, 03:39 PM
  5. Replies: 0
    Last Post: 01-24-2011, 01:10 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
-: Vuhelp Disclaimer :-
None of the files shown here are hosted or transmitted by this server. The links are provided solely by this site's users. The administrator's or staff of Vuhelp.net cannot be held responsible for what its users post, or any other actions of its users. You may not use this site to distribute or download any material when you do not have the legal rights to do so. It is your own responsibility to adhere to these terms. If you have any doubts about legality of content or you have any suspicions, feel free to contact us.
Desitoon |Vugurus|Urducell|Online Education|Indian Dramas