    Lec # 23
    PROCESS COSTING SYSTEM
    (Opening balance of work in process)


    Two methods of cost allocation

    (1) The weighted average (or averaging) method
    (2) The FIFO method.



    Weighted average method

    In the weighted average method opening stock values are added to current costs

    FIFO method

    • It is more complicated to operate
    • In process costing, it seems unrealistic to relate costs for the previous period to the current Period of activities

    Choosing the valuation method in examinations
    In order to use the weighted average or FIFO methods to account for opening work-in-process different information is needed, as follows:
    For weighted average An analysis of the opening work-in-process value
    Into cost elements (i.e. materials, labor)
    For FIFO The degree of completion of the opening work in process for each cost element.



    Lec # 25
    COSTING/VALUATION OF JOINT AND BY PRODUCTS


    Basis of Cost Allocation (For by products)

    (1) Physical Quantity Ratio
    (2) Selling Price Ratio
    (3) Hypothetical Market Value Ratio
    Classification of by product
    By product can be classified into two categories:

    1. Requiting no further process
    2. Requiting further processing

    Accounting for By Products

    (1) Income Approach
    (2) Costing Approach





    Lec#27
    MARGINAL AND ABSORPTION COSTING
    (Product costing systems)




    Cost Elements

    Direct Material, Direct Material Factory Overhead Cost
    (Variable Cost) (Variable & Fixed Cost)


    Marginal Costing

    The cost of a cost unit is presented as the total of direct materials, direct labor, direct expenses and variable overheads (but not fixed overheads)

    Marginal cost is the cost the variable cost that changes with the production of each next unit.

    (A key concept in marginal costing is that of contribution margin)

    Absorption and marginal costing

    In absorption costing, fixed manufacturing overheads are absorbed into cost units. Thus stock is valued at absorption cost and fixed manufacturing overheads are charged in the profit and loss account of the period in which the units are sold.


    In marginal costing, fixed manufacturing overheads are not absorbed into cost units, Stock is valued at marginal (or variable) cost and fixed manufacturing overheads are treated as period costs and are charged in the profit and loss account of the period in which the overheads are incurred.



    (Under absorption costing stock will include variable and fixed overheads whereas under marginal costing stock will only include variable overheads.)


    Contribution Margin

    Contribution margin = Sales - variable costs of sales

    Contribution margin is short for “contribution to fixed costs and profits


    Marginal costing: Profit calculation

    Sales Rs X
    Less: variable costs (X)
    ------------
    Contribution margin X
    Less: fixed costs (X)
    ---------------
    Profit X

    In short contribution margin less fixed cost is called profit

    Absorption costing: profit calculation

    In absorption costing this is effectively calculated in one stage as the cost of sales already includes fixed costs

    Sales X
    Less: absorption cost (X)
    ------------
    Profit X




    Marginal or absorption costing can be useful for internal management reporting


    Lec# 28
    If stock levels are rising from opening to closing balance


    Absorption Costing profit > Margin Costing profit
    (More profit) (Less profit)


    If stock levels are falling from opening to closing balance

    Absorption Costing profit < Margin Costing profit
    (Less profit) (More profit)

    (Fixed costs carried forward are charged in this period, under absorption costing)

    Sponsored Links


    If stock levels are the same

    Absorption Costing profit = Margin Costing profit
    (same profit) (Same profit)

    Reconciliation formula to learn Rs.

    Profit as per absorption costing system xxx
    Add Opening stock @ fixed FOH rate at opening date xxx
    Less Closing stock @ fixed FOH rate at closing date xxx
    -------
    Profit as per marginal costing system xxx






    (The only difference between using absorption costing and marginal costing as the basis of stock valuation is the treatment of fixed production costs.)



    Arguments against absorption costing

    In absorption costing the fixed costs do not change as a result of a change in the level of activity. Therefore such costs cannot be related to production and should not be included in the stock valuation



    Lec# 29
    COST – VOLUME – PROFIT ANALYSIS
    (Contribution Margin Approach)



    CVP stands for COST – VOLUME – PROFIT



    CVP analysis may also be used to predict profit levels at different volumes of activity based upon the assumption that costs and revenues exhibit a linear relationship with the level of activity.
    Cost-volume-profit analysis determines how costs and profit react to a change in the volume or level of activity, so that management can decide the 'best' activity level.

    Following are the assumptions which are used in CVP analysis.

    1. Variable costs and selling price (and hence contribution) per unit are assumed to be unaffected by a change in activity level.

    2. Fixed costs, whilst not affected in total by a change in the activity level, will change per unit as the activity level changes and there are more (or less) units over which to "share out" the fixed costs if fixed costs per unit change with the activity level, then profit per unit must also change.


    CVP is a relationship of four variables
    Sales ----------- Volume
    Variable cost ------------ Cost
    Fixed cost ----------- Cost
    Net income ------------ Profit

    Two approaches of CVP analysis

    (1) Contribution margin approach
    (2) Break even analysis approach



    Contribution Margin Approach & CVP Analysis

    Contribution margin contributes to meet the fixed cost. Once the fixed cost has been met the incremental contribution margin is the profit


    (Income Statement as per the marginal costing system is used as a Standard format of Income Statement to analyze the Cost-Volume-Profit relationship.)


    Sales xxx
    Variable Cost (xxx)
    ----------
    Contribution Margin xxx
    Fixed Cost (xxx)
    ----------
    Profit xxx



    (1) Physically increase in volume causes an increase in contribution margin and if there is not increase in the fixed cost because of such change, the incremental contribution margin is added in the final profits


    (2) Increase in sales price per unit causes an increase in the contribution margin, as there is not change in the volume the fixed will remain unchanged. So the incremental change is contribution margin is included into the profit.


    (3) Decrease in sales price per unit causes a decrease in the contribution margin, as there is not change in the volume the fixed will remain unchanged. So the change in contribution margin is subtracted from the profits, which result into a loss

    (Normally a decrease in sales price should case an increase in the sales volume).

    (4) Decrease in sales price per unit causes a decrease in the contribution margin, as well as an increase in volume is causing an increase in the profit, this results in an increase in profit

    1. At zero contribution margin the loss will be equal to the fixed cost

    2. Increase in variable cost reduces the contribution margin

    3. Sales – Variable cost = Contribution margin

    4. Contribution margin + Variable cost = Sales

    5. Contribution margin – Fixed cost = Profit

    6. Profit + Fixed cost = Contribution margin

    7. Sales - Variable cost = Fixed cost + Profit



    Lec#30
    COST – VOLUME – PROFIT ANALYSIS
    (Break-even Approach)



    Break-even
    Break-even is the point where sales revenue equals total cost.

    In case neither a profit nor a loss
    Profit (or loss) is the difference between contribution margin and fixed costs.
    Thus the break-even point occurs where contribution margin equals fixed costs

    Contribution Margin per unit
    Selling price per unit less variable costs per unit

    Total contribution
    Volume x (Selling price per unit less variable costs per unit)

    Target Contribution Margin
    Fixed costs + Profit target

    Target Sales in number of units
    Target Contribution Margin
    ________________________
    Unit contribution

    Contribution margin to sales ratio
    Contribution to sales ratio(C/S ratio) =Contribution Margin in Rs / Sales in Rs

    Break even sales in Rupees

    % of required amount
    Given Amount x _________________ = Required Amount
    % of given amount


    Target CM (fixed cost + target profit)
    Break even sales in Rupees = _______________________
    Contribution to sales ratio ( CM in Rs / Sale in Rs.)


    Example
    If the target contribution margin is equal to Rs. 1,000 then what would be the sales at this point?
    Now the above formula will be applied to calculate breakeven sales:
    Target CM is the given amount and its % is 25, so the sale which is 100% will be:

    100
    Rs 1,000 x ----- = Rs 4,000 break even sale in Rs.

    25
    OR

    Rs 1,000
    -------- = Rs. 4,000 break even sale in Rs
    25

    So,
    Fixed cost
    Break even Sales in Rs. = -------------
    C/S ratio

    Break even sales in units

    Simple formula


    Break even sales in Rupees
    ------------------------------------= number of units
    Sales price per unit







    Direct formula
    Target CM (Fixed costs + Profit target)
    -------------------
    CM per unit (Selling price per unit less variable costs per unit)




    Lec# 31
    BREAK EVEN ANALYSIS – MARGIN OF SAFETY



    Margin of Safety (MOS)

    The margin of safety is the difference between budgeted sales volume and break-even sales volume; it indicates the vulnerability of a business to a fall in demand.

    Margin of safety=Budgeted sales – Break-even sales



    MOS (margin of safety) ratio
    MOS (Margin of safety=Budgeted sales)
    MOS (margin of safety) ratio = __________________ x 100
    Budgeted Sales
    OR

    Budgeted profit
    Margin of safety ratio = ________________________ x 100
    Budgeted contribution margin

    OR

    MOS Ratio profit / contribution margin
    Different ways of calculation of margin of safety

    (1) Based on Budgeted sales
    Budgeted sales – Break-even sales



    (2) Using Budget profit
    Budgeted profit
    _______ _______________ x 100
    Budgeted contribution margin

    (3) Using profit and contribution ratio
    Profit to sales ratio
    ____________________ x 100
    Contribution to sales




    Lec#32
    BREAKEVEN ANALYSIS – CHARTS AND GRAPHS




    The chart or graph is constructed as follows:

    • Plot fixed costs, as a straight line parallel to the horizontal axis

    • Plot sales revenue and variable costs from the origin

    • Total costs represent fixed plus variable costs.
    (1) The point at which the sales revenue and total cost lines intersect indicates the breakeven level of output.

    (2) By multiplying the sales volume by the unit price at the break-even point the level of revenue needed to break even can be determined.

    (3) The chart is normally drawn up to the budgeted sales volume.
    (4) The difference between the budgeted sales volume and break-even sales volume is referred to as the margin of safety.



    Lec#33
    WHAT IS A BUDGET?



    Budget

    A budget is a plan expressed in quantitative, usually monetary terms, covering a specific period of time, usually one year.


    Two basic classes of budget

    (1) Cash budget
    (2) Operating budget



    Cash budget
    Capital budgets are directed towards proposed expenditures for new projects
    And often require special financing.

    Operating budget

    The operating budgets are directed towards achieving short-term operational goals of the organization, for instance, production or profit goals in a business firm. Operating budgets may be sub-divided into various departmental or functional budgets.



    Characteristics of a budget
    It is prepared in advance and is derived from the long, term strategy of the organization.
    It relates to future period for which objectives or goals have already been laid down.
    It is expressed in quantitative form, physical or monetary units, or both.

    Different types of budgets
    (1) Sales. Budget
    (2) Production Budget
    (3) Administrative Expense Budget
    (4) Raw material Budget, etc

    All these sectional budgets are afterwards integrated into a master budget- which represents an overall plan of the organization
    A budget helps in following ways

    1. It brings about efficiency and improvement in the working of the organization.
    2. way of communicating the plans to various units of the organization. By establishing the divisional, departmental, sectional budgets, exact responsibilities are assigned. It thus minimizes the possibilities of buck-passing if the budget figures are not met.
    3. Way or motivating managers to achieve the goals set for the units.
    4. It serves as a benchmark for controlling on going. Operations.
    5. It helps in developing a team spirit where participation in budgeting is encouraged.
    6. It helps in reducing wastage's and losses by revealing them in time for corrective action.
    7. It serves as a basis for evaluating the performance of managers.
    8. It serves as a means of educating the managers.

    Budgetary control
    The exercise of control in the organization with the help of budgets is known as budgetary control.

    Process of budgetary control
    (i) preparation of various budgets
    (ii) (ii) continuous comparison of actual performance with budgetary
    Performance
    (iii) Revision of budgets in the light of changed circumstances.


    Budget controller
    The Chief Executive is finally responsible for the budget programmed, it is better if a large part of the supervisory responsibility is delegated to an official designated as Budget Controller or Budget Director.

    Fixation of the Budget Period

    Budget period' means the period for which a budget is prepared and employed. The budget period depends upon the nature of the business and the control techniques.
    Forecast
    A forecast is an estimate of the future financial conditions or operating results.
    A forecast may be prepared in financial or physical terms for sales, production cost, or other resources required for business. Instead of just one forecast a number of alternative forecasts may be considered with a view to obtaining the most realistic overall plan.


    Preparing budgets


    After the forecasts have been finalized the preparation of budgets follows. The budget activity starts with the preparation of the said budget.

    Production budget: on the basis of sales budget and the production capacity available

    Financial budget (i.e. cash or working capital budget): will be prepared on the basis of sale forecast and production budget.


    (All these budgets are combined and coordinated into -a master budget)


    Fixed and Flexible Budgets
    A fixed budget is based on a fixed volume of activity, 11 may
    lose its effectiveness in planning and controlling if the actual capacity utilization is different from what was planned for any particular unit of time e.g. a month or a quarter.

    The flexible budget is more useful for changing levels of activity, as it considers fixed and variable costs separately. Fixed costs, as you are aware, remain unchanged over a certain range of output such costs change when
    There is a change in capacity level. The variable costs change in direct proportion to output.

    (If flexible budgeting approach is adopted, the budget controller can analyze the variance between actual costs and budgeted costs depending upon the actual level of activity attained during a period of time.)


    Objective of Budget

    (1) Profit maximization
    (2) Maximization of sales
    (3) Volume growth
    (4) To compete with the competitors
    (5) Development of new areas of operation.
    (6) Quality of service
    (7) Work-force efficiency.


    Division of Budgets

    (1) Functional Budget
    (2) Master Budget


    vuhelp MGT402.JPG



    Lec#34
    PRODUCTION & SALES BUDGET


    Budgets can be classified into different categories on the basis of Time, Function, or Flexibility.


    Rolling budget

    Budget for a year in advance will always be there. Immediately after a month, or a quarter, passes, as-the case may be, a new budget is prepared for a twelve months. The figures for the month/quarter, which has rolled down, are dropped and the figures for the next month /quarter are added.

    Example,
    If a budget has been prepared for the year 19X7, after the expiry of the first quarter ending 31st March 19X7, a new budget forth full year ending 31ft March, 19X8 will be prepared by dropping the figures for the quarter which has past (i.e. quarter ending 31st March 19X7) and adding-the figures for the new quarter-ending 31st March 19X8.


    Sales budget
    Sales Budget generally forms the fundamental basis on which all other budgets are built the budget is based on projected sales to be achieved in a budget period. The Sales Manager is directly responsible for the preparation and execution of this budget.

    Lec#35
    PRODUCTION & SALES BUDGET (Contd.)



    Production budget
    This budget provides an estimate of the total volume of production distributed product-wise with the scheduling of operations by days, weeks and months and a forecast of the inventory of finished products.
    Generally, the production budget is based on the sales -budget.

    The production budget is prepared after taking into consideration several factors like:
    (i) Inventory policies.
    (ii) Sales requirements
    (iii) Production stability
    (iv) Plant capacity
    (v) Availability of materials and labor
    (vi) Time taken in production process, etc.

    Lec#36
    FLEXIBLE BUDGET (not completed)



    The preparation of a flexible budget results from the development of formulas for each department and for each account within a department or cost center. The formula for each account indicates the fixed amount and/or a variable rate. The fixed amount and variable rate remain constant within prescribed ranges of activity. The variable portion of the formula is a rate expressed in relation to a base such as direct labor hours, direct labor cost or machine hours.

    Capacity and volume

    The terms "capacity" and "volume" (or activity) are used in connection with the construction and use of both fixed and flexible budgets.

    Capacity is that fixed amount
    Volume is the variable factor in business.


    Theoretical Capacity
    The theoretical capacity of a department is its capacity to produce at full speed without interruptions

    Expected Actual Capacity

    Expected actual capacity is based on a short-range outlook. The use of expected actual capacity is feasible with firms whose products are of a seasonal nature» and market and style changes allow price adjustments according to competitive conditions and customer demands.


    Lec#37
    FLEXIBLE BUDGET (Contd.)


    Analysis of Cost Behavior
    The success of a flexible budget depends upon careful study and analysis of the relationship of expenses to volume of activity or production and results in classifying expenses as fixed, variable, and semi variable,


    Fixed Expenses
    A fixed expense remains the same in total as activity increases or decreases.

    In the short run, some fixed expenses, some times called programmed fixed expenses, will change because of changes in the volume of activity or for such reasons as changes in the number and salaries of the management groups.

    Variable Expenses
    A variable expense is expected to increase proportionately with an increase in activity and decrease proportionately with a decrease in activity.

    Variable expenses include the cost of supplies, indirect factory labor, receiving, storing, rework, perishable tools, and maintenance of machinery and tools. A measure of activity – such as direct labor hour or dollars.


    Lec#38
    TYPES OF BUDGET


    Cash Budget
    Determining the future is a summary of the firm's expected cash inflows and outflows over a particular period of time.

    Objective
    Cash budget is to enable the firm to meet all its commitments in time
    And at the same time prevent accumulation at any lime of unnecessary large cash balances with it:



    Format of Cash Budget


    XYZ Ltd
    Cash budget
    For the month of XXX – XXX

    Opening balance
    Add Receipts (Anticipated cash
    Receipt from all sources)
    Less Payments (Anticipated utilization of cash)
    Excess / Deficit
    Bank barrowing / Overdraft
    Closing balance


    Lec#39
    COMPLEX CASH BUDGET & FLEXIBLE BUDGET


    Flexible budget
    The Flexible Budget is designed to change in accordance with the level of activity attained. Such a budget is prepared after considering the fixed and
    Variable elements of cost and the changes that may be expected for each item at various levels of Operations


    LEC#40
    FLEXIBLE & ZERO BASE BUDGETING



    Controlling ratios
    Budget is a part of the planning process.

    (1) Activity Ratio
    (2) Capacity Ratio
    (3) Efficiency Ratio

    If the ratio works out to 100 per cent or more, the trend is taken as favorable, if the ratio is less than 100 per cent, the indication is taken
    as unfavorable.

    Activity Ratio:

    Standard hours for actual production
    Activity Ratio = ___________________________________ x 100
    Budgeted hours


    Capacity Ratio:


    Actual hours worked
    Capacity Ratio = ____________________ x 100
    Budgeted hours


    Efficiency Ratio:


    Standard hours for actual production
    Efficiency Ratio = ____________________________________ x 100
    Actual hours worked

    Performance budgeting
    A performance budget presents the operations of an organization in terms of functions, programmers, activities, and projects.

    The primary purpose of traditional budget particularly in government administration is to ensure financial control and meet the requirements of legal accountability, that is, to ensure that appropriation.

    Objectives of PB

    (1) to coordinate the physical and financial aspects
    (2) To improve the budget formulation, review and decision-making at all levels of management
    (3) To facilitate better appreciation and review by controlling Authorities (legislature, Board of Trustees or Governors, etc.) as the presentation is more
    Purposeful and intelligible
    (4)To make more effective performance audit possible
    (5) To measure progress towards long-term objectives which are envisaged in a development plan

    Zero base Budgeting
    Zero base Budgeting technique suggests that an organization should not only make decisions about the proposed new programmers, but should also, from time to time, review the appropriateness of the existing.
    The concept of Zero base Budgeting has been accepted for adoption in the departments of the Central Government and some State Governments.

    Lec#41
    DECISION MAKING IN MANAGEMENT ACCOUNTING



    Costs appropriate to a specific management decision

    The amount by which costs increase and benefits decrease as a direct result of a specific management decision’ Relevant benefits are ‘the amounts by which costs decrease and benefits increase as a direct result of a specific management decision’


    Incremental costs
    An incremental cost can be defined as a cost which is specifically incurred by following a course of action and which is avoidable if such action is not taken.



    Non-incremental costs
    These are costs, which will not be affected by the decision at hand. Non-incremental costs are non-relevant costs because they are not related to the decision at hand

    The labor cost is non-relevant

    Opportunity costs (relevant cost)
    An opportunity cost is a level of profit or benefit foregone by the pursuit of a particular course of action.


    Sunk cost(non-relevant cost)
    A sunk cost is a cost that the already been incurred and cannot be altered by any future decision
    Sunk costs are the opposite of opportunity costs in that they are not incorporated in the decision making process even though they have already been recorded in the books and records of the enterprise.


    LEC#42
    DECISION MAKING

    Q: why companies close down temporarily?
    ANS: Companies are often faced with the problem of whether to close down temporarily a part of the plant during periods of low demand.
    Arguments against shut-down
    (a) If the company continues operation, expenses that would be incurred with the closing down of the plant will be saved; e.g. an increase in factory security.
    (b) Continued operation means saving (he expenses that will otherwise be incurred if the plant is reopened again at a later stage.
    (c) A shut-down for a short period of fine will not eliminate all costs. Rent, rates, depreciation and insurance will have to be incurred during the shutdown period.
    (d) If the factory is shut down, this will affect not only morale but also its market standing if it cannot meet consumer demand.

    The role of fixed costs
    If the decrease or increase in the level of activity affects fixed costs then these costs should be considered differential costs.
    It is generally accepted that if the plant has excess capacity then new or additional volume may be accepted if the selling price ii greater than variable costs. In such a situation, fixed costs arc not relevant if they remain fixed at an increased level of output

    The role of variable costs
    In differential cost studies, if the plant is not operating at practical capacity owing to lack of orders, variable costs usually represent the differential cost whether they are incremental or avoidable. The term refers to those costs that will change. It is often assumed that the variable cost per unit will remain constant regardless of the level of activity.

    Lec#43
    DECISION MAKING (Contd.)


    Relevant Costs

    Decision making should be based on relevant costs.

    • Relevant costs are future costs
    • Relevant costs are cash flows
    • Relevant costs are incremental costs

    Differential Costs and Opportunity Costs
    Relevant costs are also differential costs and opportunity costs.
    • Differential cost is the difference in total cost between alternatives.
    For example, if decision option A costs Rs. 300 and decision option B costs Rs. 360, the differential costs is Rs. 60.
    • An opportunity cost is the value of the benefit sacrificed when one course of action is chosen in preference to an alternative.

    Controllable and Uncontrollable Costs

    Controllable costs are items of expenditure which can be directly influenced by a given manger within a given time span.

    As a general rule, committed fixed costs such as those costs arising form the possession of plant, equipment and buildings (giving rise to deprecation and rent) are largely uncontrollable in the short term because they have been committed by longer-term decisions.

    Fixed and Variable Costs

    • Variable costs will be relevant costs.
    • Fixed costs are irrelevant to a decision


    Attributable Fixed Costs
    There might be occasions when a fixed cost is a relevant cost, and you must be aware of the distinction ‘specific’ or ‘directly attributable’ fixed costs, and general fixed overheads


    Absorbed Overhead and fixed overhead
    Absorbed overhead is a national accounting cost and hence should be ignored for decision making purposes.
    It is overhead incurred which may be relevant to a decision.

    General fixed overheads are those fixed overheads which will be unaffected by decisions to increase or decreased the scale of operations, perhaps because they are an apportioned share of the fixed costs of items which would be completely unaffected by the decision.
    General fixed overheads are not relevant in decision making.




    Lec#44
    DECISION MAKING
    CHOICE OF PRODUCT (PRODUCT MIX) DECISIONS



    Make or Buy Decisions and Limiting Factors
    In a situation where a company must subcontract work to make up a shortfall in its won production capability, its total costs are minimized if those components/products subcontracted are those with the lowest extra variable cost of buying per unit of limiting factor saved by buying.

    Lec#45
    DECISION MAKING (Contd.)


    Shut Down Decisions

    (1) Whether or not to shut down a factory, department, or product line either because it is making a loss or it is too expensive to run.
    (2) If the decision is to shut down, whether the closure should be permanent or temporary.


    ONE-OFF CONTRACTS
    The decision to accept or reject a contract should be made on the basis of whether or not the contract increases contribution and profit.

    Other factors to consider in the one-off contract decision.
    A. The acceptance of the contract at a lower price may lead other customers to demand lower prices as well.
    B. There may be more profitable ways of using the spare capacity.
    C. Accepting the contract may lock up capacity that could be used for future full-price business.
    D. Fixed costs may, in fact, if the contract is accepted.
    Last edited by viki; 06-20-2010 at 09:19 AM.
    :o:o--------------------------------------------------------------------------------------:o:o
    [B]The more knowledge you have, the greater will be your fear of Allah.[/B]

    Please Join My [B]Group Vuhelp[/B][B], Birthday Wishing, Daily Hadees[/B] [CODE][B]http://vuhelp.net/groups/vuhelp.html[/B]
    [B]http://vuhelp.net/groups/birthday-wishing.html[/B]
    [B]http://vuhelp.net/groups/daily-hadees.html[/B][/CODE]
    [CENTER][B][COLOR="Red"][SIZE="4"]Email: [email]viki@vuhelp.net[/email][/SIZE][/COLOR][/B][/CENTER]

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. MGT402 Cost & Management Accounting short notes for download
    By Support in forum Vu Handouts and Short Notes
    Replies: 0
    Last Post: 11-27-2010, 01:54 AM
  2. MGT402 - Cost & Management Accounting fall 2010
    By Xpert in forum Virtual University Handouts
    Replies: 0
    Last Post: 10-16-2010, 08:26 PM
  3. MGT402- Cost &Management Accounting (Session - 4) June 2010
    By viki in forum MCQ's & Quiz Discussion
    Replies: 0
    Last Post: 06-03-2010, 06:55 AM
  4. MGT402 Cost and Management Accounting Quiz May 17,2010
    By viki in forum MCQ's & Quiz Discussion
    Replies: 4
    Last Post: 05-19-2010, 09:26 PM
  5. Replies: 0
    Last Post: 05-10-2010, 11:00 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
-: Vuhelp Disclaimer :-
None of the files shown here are hosted or transmitted by this server. The links are provided solely by this site's users. The administrator's or staff of Vuhelp.net cannot be held responsible for what its users post, or any other actions of its users. You may not use this site to distribute or download any material when you do not have the legal rights to do so. It is your own responsibility to adhere to these terms. If you have any doubts about legality of content or you have any suspicions, feel free to contact us.
Online Education | JhelumSoft