is ka solution kab aya ga?
Software Engineering II CS605View more random threads:
- CS302 Digital Logic Design Assignment 6 Deadline 22 July...
- MTH601 Operations Research Assignment No. 01 Solution and...
- CS602 Computer Graphics Assignment No. 01 Solution and...
- MTH001 Spring 2010 May 10
- Circuit Theory (Phy301) Assignment No: 2 Ideal Solution...
- CS403 - Database Management Systems Assignment 6 Deadline...
- CS301 Assignment # 4
- IT430 Assignment No.4 (Take Idea !)
- CS504 Assignment 2 Solution Spring 2010 May 5
- MGMT627 Project Management Assignment No.1 Fall Semester...
Assignment 4 Solution
Sponsored Links
Question:
Suppose you are a project manager of a company xyz. You have been asked to compute the earned value analysis of a software project. The software project has 70 planned work tasks that are estimated to require 620 person-days to complete. At the time you have been asked to do the earned value analysis, 13 tasks have been completed. However, the project schedule indicates that 16 tasks should have been completed. The following scheduling data in person-days are available:
You are required to compute the SPI, schedule variance, percent scheduled for completion, percent complete, CPI, and cost variance for the project
Solution:
Budgeted cost of work scheduled (BCWS)
11 + 8 + 5 + 13 + 11 + 15 + 8 + 7 + 10 + 12.5 + 6 + 3 + 10 + 5 + 6 = 130.5
Budgeted cost of work performed (BCWP):
11 + 8 + 5 + 13 + 11 + 15 + 8 + 7 + 10 + 12.5 + 6 + 3 = 109.5
Budgetat Completion
620
Schedule performance index, SPI = BCWP/BCWS = 109.5/130.5 = 0.83
Schedule variance, SV = BCWP – BCWS = 109.5 - 130.5 = -21
Percent scheduled for completion = BCWS/BAC = 130.5/620 = 0.21
Percent complete = BCWP/BAC = 109.5/620 = 0.17
Actual Cost of Work Performed
10 + 9 + 4 + 13.5 + 11 + 16 + 10 + 7 + 9 + 13 + 5 + 5 = 112.5
Cost performance index, CPI = BCWP/ACWP = 109.5/112.5 = 0.97
Cost variance, CV = BCWP – ACWP = 109.5 – 112.5 = -3