    Software Project Management
    Assignment # 04
    Spring 2011
    Marks: 20
    Due Date
    Your assignment must be uploaded before or on 16th June 2011.

    Uploading instructions:

    Please view the Assignment Submission Process document provided to you by the Virtual University for uploading assignments.

    • Assignment should be in .doc format.
    • Save your assignment with your ID (e.g. bx020200786.doc).
    • Assignment submission through email is highly discouraged.

    Rules for Marking:

    It should be clear that your assignment will not get any credit if:
    • The assignment is submitted after due date.
    • The submitted assignment file is corrupted.
    • The assignment is copied.
    Note:
    Your answer must follow the below given specifications. You will be assigned zero marks if you do not follow these instructions.
    • Font style: “Times New Roman”
    • Font color: “Black”
    • Font size: “12”
    • Bold for heading only.
    • Font in Italic is not allowed at all.
    • No formatting or bullets are allowed to use.

    Assignment:



    Q.No.1


    Your software company got a project from the sale company for the development of the website to manage their visitors. They also want to keep track of their frequent visitors for sales follow up.

    A small team which consists of website manager, web developer, content administrator, web administrator and sales manager will develop and manage this project.

    Following are the given activities that you perform:

    Project planning
    Website construction
    Content review
    Usability testing
    Installation of tracking software
    Ongoing review of visitors
    Sales follow up to frequent users

    Following are the given scale that you will use:

    R=Responsible, C=Consulted, A=Accountable, I=Informed.

    You have to create a responsibility assignment matrix by using the above scale, task and development team. In simple words you have to map the work of the project to the peoples responsible for performing that work using the given scale.

    Sponsored Links


    Attached Files Attached Files

  2. Sponsored Links

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 0
    Last Post: 04-06-2012, 07:45 PM
  2. cs615 gdb idea solution spring 2011 on 6 july
    By Xpert in forum GDB Discussion
    Replies: 0
    Last Post: 07-07-2011, 12:03 AM
  3. Replies: 0
    Last Post: 06-21-2011, 05:26 PM
  4. Replies: 0
    Last Post: 06-02-2011, 06:48 PM
  5. Replies: 2
    Last Post: 05-01-2011, 04:55 AM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
-: Vuhelp Disclaimer :-
None of the files shown here are hosted or transmitted by this server. The links are provided solely by this site's users. The administrator's or staff of Vuhelp.net cannot be held responsible for what its users post, or any other actions of its users. You may not use this site to distribute or download any material when you do not have the legal rights to do so. It is your own responsibility to adhere to these terms. If you have any doubts about legality of content or you have any suspicions, feel free to contact us.
Online Education | JhelumSoft