    Question No.01

    You are working in sigma tech software house. Mr. SHAH is in the process of Source Selection for a contract for your project. He is planning to use weighing process for source selection. There are five vendors being considered. There are two deciding factors price (weight-age 60), quality (weight-age 40). The scores of five vendors that in Mr. SHAH Team have computed are displayed in the table below. Which vendor will among these five should be chosen and how?


    cs615.jpg


    Question No.02

    Mr. UMAR FAROOQ is the Project Manager for a Defiance project. The scope of the project has been completed. He receives a request for a new module to be developed as part of this project. What should he do next? Which option he would select and why?
    a. He should approach the Senior Management and ask them for a new module to be developed as part of this project.
    b. He should send the request to Change Control Board for approval.
    c. Since the project scope is completed. He should inform the customer that this change cannot be done as part of the project.


    Sponsored Links
    :o:o--------------------------------------------------------------------------------------:o:o
    [B]The more knowledge you have, the greater will be your fear of Allah.[/B]

    Please Join My [B]Group Vuhelp[/B][B], Birthday Wishing, Daily Hadees[/B] [CODE][B]http://vuhelp.net/groups/vuhelp.html[/B]
    [B]http://vuhelp.net/groups/birthday-wishing.html[/B]
    [B]http://vuhelp.net/groups/daily-hadees.html[/B][/CODE]
    [CENTER][B][COLOR="Red"][SIZE="4"]Email: [email]viki@vuhelp.net[/email][/SIZE][/COLOR][/B][/CENTER]

  2. #2
    Junior Member
    Join Date
    Jul 2010
    Posts
    1
    please post the solution of this assignment.

  3. #3
    Senior Member viki's Avatar
    Join Date
    May 2010
    Posts
    2,132

    idea solution

    cs615 1.jpg


    a. Vendor 1
    b. Vendor 2
    c. Vendor 3
    d. Vendor 4
    e. We need to compute the following for all the vendors - (0.4*Price + 0.6*Quality). The scores come out to be vendor 1 - 10.4, vendor 2 - 10, vendor 3 - 9.6, and vendor 4's 11. Since vendor 4 has the highest score, it should get selected.


    You are the Project Manager for XYZ project. The scope of the project has been completed. You receive a request for a new module to be developed as part of this project. What should you do next?
    a. You should approach the Project sponsor and ask her for a new module to be developed as part of this project.
    b. You should approach the Senior Management and ask them for a new module to be developed as part of this project.
    c. You should send the request to Change Control Board for approval.
    d. Since the project scope is completed you should inform the customer that this change cannot be done as part of the project.
    Answer:
    d. As the scope is completed, the project is complete. Additional work should be done as part of a new project.
    :o:o--------------------------------------------------------------------------------------:o:o
    [B]The more knowledge you have, the greater will be your fear of Allah.[/B]

    Please Join My [B]Group Vuhelp[/B][B], Birthday Wishing, Daily Hadees[/B] [CODE][B]http://vuhelp.net/groups/vuhelp.html[/B]
    [B]http://vuhelp.net/groups/birthday-wishing.html[/B]
    [B]http://vuhelp.net/groups/daily-hadees.html[/B][/CODE]
    [CENTER][B][COLOR="Red"][SIZE="4"]Email: [email]viki@vuhelp.net[/email][/SIZE][/COLOR][/B][/CENTER]

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 0
    Last Post: 12-12-2014, 08:21 PM
  2. CS615 Software Project Management Assignment No. 01 November 2014
    By Entboy in forum Assignments & Solutions
    Replies: 0
    Last Post: 11-17-2014, 07:55 PM
  3. Replies: 2
    Last Post: 06-06-2012, 03:26 PM
  4. Replies: 1
    Last Post: 04-13-2012, 11:32 AM
  5. Replies: 0
    Last Post: 08-28-2010, 06:04 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
-: Vuhelp Disclaimer :-
None of the files shown here are hosted or transmitted by this server. The links are provided solely by this site's users. The administrator's or staff of Vuhelp.net cannot be held responsible for what its users post, or any other actions of its users. You may not use this site to distribute or download any material when you do not have the legal rights to do so. It is your own responsibility to adhere to these terms. If you have any doubts about legality of content or you have any suspicions, feel free to contact us.
Online Education | JhelumSoft