Question no 1:View more random threads:
- MGT502 Organizational Behavior Assignment No.1 Solution...
- MGMT628 Assignment No. 1 spring fall 14 November 2011
- MGT211 Introduction to Business SEMESTER SPRING April 2012...
- MKT611 Marketing Research Assignment No.1 Solution Spring...
- MTH401 ASSIGNMENT 02 Differential Equation idea solution...
- eng201 full solution assignment no 3 December 2011-2012
- need assignment solution
- FIN630 VU Current Assignment No. 2 Fall 2011 Last date 13...
- Mgt602 Entreprenureship Assignment No. 1 spring fall...
- IT430 assignment no 3 semester fall 20 December 2011
An XYZ Organization wants to develop MIS system. Using MIS system they can store their employee’s
information. A feasibility report is generated for estimating the cost, resources and time duration and the
project size. Project Manager determines the amounts of effort in person months based on his earlier
experience for the development phase of the MIS system, and express the required cost for a particular
phase of the MIS system. Deliverables of the MIS system is achieving through the user view.
1. You have to suggest that which Estimation Technique can be used for estimating the size of the
MIS system and why?
5 Marks
2. Mention five advantages of the suggested Estimation Technique.