View more random threads:
- HRM624 Final term 2009
- MGT610 Business Ethics Spring 2009 Final Term Paper
- CS304 Final Term Paper Fall 2009 Unsolved
- cs304 Object Oriented Programming download the midterm...
- MGT411- Money & Banking Spring 2009 Final Term Paper
- MGT502 Organizational Behaviour MIDTERM EXAMINATION ...
- PAK301 Pakistan Studies Spring 2009 Final Term Paper
- ENG301 Business Communication Spring 2009 Final Term Paper
- CS402 Theory of Automata Spring 2009 Final Term Paper
- CS605 Software Engineering II Spring 2009 Final Term Paper
FINALTERM EXAMINATION
Spring 2009
MGMT627 Project Management
Marks: 81
Question No: 1 ( Marks: 1 ) - Please choose one
Project management specialists frequently distinguish between weak and strong matrix
structures. Identify the chief characteristic of a weak matrix.
- Team members are not fully trained to do the job
- The functional manager has relatively more influence in making decisions than the project manager
- Management reserve is rapidly being depleted
- Re-baselining occurs frequently
Question No: 2 ( Marks: 1 ) - Please choose one
High production costs are typically found at which of the following Project Life Cycle
(PLC) phases?
- Maturity phase of the PLC
- Growth phase of the PLC
- Decline phase of the PLC
- Introduction phase of the PLC
Question No: 3 ( Marks: 1 ) - Please choose one
Which of the following is included in Project Scope Management?
- Plan development
- Project plan execution
- Integrated change control
- Initiation
Question No: 4 ( Marks: 1 ) - Please choose one
Which of the following statements is TRUE about scope management?
- It entails managing the project's work content
- It is a subset of configuration management and as such is performed by scope management specialists
- It is concerned with defining and controlling what is or is not included in the project
- It is not a concern of the project manager
Question No: 5 ( Marks: 1 ) - Please choose one
Which of the following statements best describes the project life-cycle?
- Project concept, project execution, and project reporting
- Project planning, work authorization, and project reporting
- Project planning, project control, project definition, work breakdown structure development and project termination
- Project concept, project planning, project execution, and project close-out
Question No: 6 ( Marks: 1 ) - Please choose one
All of the following are activities of the Project Engineering Manager, EXCEPT:
- Process flow sheets
- Equipment data specifications
- Process liaison
- Bid analysis
Question No: 7 ( Marks: 1 ) - Please choose one
Which of the following shows the impact on results of changes in assumptions?
- Controlled variation
- Scenario analysis
- Financial package blueprint
- Feasibility analysis
Question No: 8 ( Marks: 1 ) - Please choose one
All of the following factors affect the estimation decision, EXCEPT:
- Size of project
- Size of team
- Past experience
- Length of schedule
Question No: 9 ( Marks: 1 ) - Please choose one
Which of the following is NOT a formal method of Selecting Projects?
- The Sacred Cow
- The Operating Necessity
- The Competitive Necessity
- Comparative Benefit Model
Question No: 10 ( Marks: 1 ) - Please choose one
The success of a project depends critically upon which of the following?
- Effort
- Care
- Skill
- All of the given options
Question No: 11 ( Marks: 1 ) - Please choose one
Which of the following is NOT an input to project plan execution?
- Work authorization system
- Project plan
- Corrective action
- Preventive action
Sponsored Links
Question No: 12 ( Marks: 1 ) - Please choose one
Which of the following spells out clearly defined and agreed-upon goals in beginning of
project?
- Project Mission
- Project Schedule
- Project Execution Plan
- Project Scope
Question No: 13 ( Marks: 1 ) - Please choose one
All of the following are included in the Functional Level Planning, EXCEPT:
- Coordination of work activities
- Commitment to group goals
- Vertical & lateral communication
- Lateral communication
Question No: 14 ( Marks: 1 ) - Please choose one
All of the following are external economic variables for strategic planning in the tire
industry, EXCEPT:
- Forecast of industry
- Division of market
- Competition
- Steel and chemical output
Question No: 15 ( Marks: 1 ) - Please choose one
Who among the follolwing is responsible to provide technical directions to any problem?
- Assistant project manager
- Program manager
- Line manager
- Project manager
Question No: 16 ( Marks: 1 ) - Please choose one
Which of the following types of managers is the true technical expert?
- Program manager
- Line manager
- Project manager
- Assistant project manager
Question No: 17 ( Marks: 1 ) - Please choose one
Which of the following defines the size of the project?
- Project plan
- Project scope
- Project charter
- Work breakdown structure
Question No: 18 ( Marks: 1 ) - Please choose one
Which of the following is prepared before project approval?
- Project scope document
- Project charter
- Business case
- Project scope statement
Question No: 19 ( Marks: 1 ) - Please choose one
In scope verification process, who will give the formal acceptance of work completion?
- Top management
- Customers
- Stake holders
- Project manager
Question No: 20 ( Marks: 1 ) - Please choose one
Which of the following is the cause of scope creep?
- Cost reduction
- Cost overrun
- Cost allocation
- Cost maintenance
Question No: 21 ( Marks: 1 ) - Please choose one
How is the earliest time denoted?
- TL
- TE
- ET
- LT
Question No: 22 ( Marks: 1 ) - Please choose one
The earliest and latest times, are which of the following?
- Dependent variables
- Random variables
- Independent variables
- Fixed values
Question No: 23 ( Marks: 1 ) - Please choose one
An event, represents which of the following?
- Beginning of an activity
- Ending of an activity
- Beginning or ending of an activity
- Duration of an activity
Question No: 24 ( Marks: 1 ) - Please choose one
In CPM, which of the following in each activity is/are considered?
- Time
- Performance
- Cost and performance
- Time and cost
Question No: 25 ( Marks: 1 ) - Please choose one
Printers and plotters, prefer to draw which of the following?
- Circle
- Square
- Dotted line
- Straight line
Question No: 26 ( Marks: 1 ) - Please choose one
In precedence diagram, what does dotted line indicates?
- Event
- Relationship
- Slack
- Critical path
Question No: 27 ( Marks: 1 ) - Please choose one
Who among the following is responsible for the development of operational tools?
- Functional unit
- Program office
- Departments
- Supervisor
Question No: 28 ( Marks: 1 ) - Please choose one
How many types of pricing reports are there?
- 4
- 6
- 8
- 10
Question No: 29 ( Marks: 1 ) - Please choose one
Which of the following have NO relative impact on price level?
- Competitive prices
- Customer budget
- Bidder s cost estimate
- Life-cycle cost
Question No: 30 ( Marks: 1 ) - Please choose one
Which of the following refers to how a product looks, feels, sounds, tastes, or smells?
- Affordability
- Conformance
- Durability
- Aesthetics
Question No: 31 ( Marks: 1 ) - Please choose one
Which of the following is referred to as the management section of quality management
by PMBOK?
- Quality control
- Quality assurance
- Total quality control
- Process control charts
Question No: 32 ( Marks: 1 ) - Please choose one
Which of the following is viewed as a vertical teamwork between managerial and non managerial
personnel?
- Performance
- Empowerment
- Continuous improvement
- Planning
Question No: 33 ( Marks: 1 ) - Please choose one
Empowerment, encourages which of the following?
- Responsibility
- Authority
- Innovation
- Motivation
Question No: 34 ( Marks: 1 ) - Please choose one
Which of the following means Quality related to price ?
- Value
- Quality control
- Customer satisfaction
- Price control
Question No: 35 ( Marks: 1 ) - Please choose one
The information provided by the Kano model, relates to which of the following?
- Customer satisfaction
- Value analysis
- Quality control
- Price control
Question No: 36 ( Marks: 1 ) - Please choose one
Process Analysis, is a function of which of the following?
- Performance Analysis
- Quality Metrics
- Process Improvement Plan
- Quality Improvement Plan
Question No: 37 ( Marks: 1 ) - Please choose one
How many tools are used for quality improvement?
- Six
- Seven
- Eight
- Nine
Question No: 38 ( Marks: 1 ) - Please choose one
What is the ratio of output to input called?
- Efficiency
- Effectiveness
- Productivity
- Quality
Question No: 39 ( Marks: 1 ) - Please choose one
Productivity, is an output input agreement on consideration of which of the following?
- Quality and time
- Competitiveness and time
- Efficiency and time
- Effectiveness and time
Question No: 40 ( Marks: 1 ) - Please choose one
Which of the following defines how & when various stakeholders receive information &
communicate with each other?
- Site Waste Management Plan
- Communication Management Plan
- Chemicals Management Plan
- Debt Management Plan
Question No: 41 ( Marks: 1 ) - Please choose one
Which of the following refers to the interpersonal influence modes that a project manager
can use?
- Leadership style
- Motivation style
- Communication style
- Controlling style
Question No: 42 ( Marks: 1 ) - Please choose one
The development of the overhead rates, is a function of how many separate elements?
- Two
- Three
- Four
- Five
Question No: 43 ( Marks: 3 )
For the construction of a network, how many inputs are required?
Question No: 44 ( Marks: 3 )
How can quality be achieved in a project?
Question No: 45 ( Marks: 3 )
What are the objectives of procurement planning?
Question No: 46 ( Marks: 5 )
What are the characteristics of effective communication?
Question No: 47 ( Marks: 5 )
Differentiate between preliminary project scope statement and detailed project
scope statement.
Question No: 48 ( Marks: 10 )
Discuss the method of preparing the schedules. Also explain its importance.
Question No: 49 ( Marks: 10 )
If a firm is using fixed price contract, how does it get advantage over others?
:o:o--------------------------------------------------------------------------------------:o:o
[B]The more knowledge you have, the greater will be your fear of Allah.[/B]
Please Join My [B]Group Vuhelp[/B][B], Birthday Wishing, Daily Hadees[/B] [CODE][B]http://vuhelp.net/groups/vuhelp.html[/B]
[B]http://vuhelp.net/groups/birthday-wishing.html[/B]
[B]http://vuhelp.net/groups/daily-hadees.html[/B][/CODE]
[CENTER][B][COLOR="Red"][SIZE="4"]Email: [email]viki@vuhelp.net[/email][/SIZE][/COLOR][/B][/CENTER]
There are currently 1 users browsing this thread. (0 members and 1 guests)